Concrete footings for main entrance posts are done. Rebar placement has started. Now we see the dimensions of the stormwater pond. We are still on track to poor the monolithic slab on May 2.
26April2019 – Main entrance from driveway
26April2019 – Looking N to S at main entrance
26April2019 – NE corner of facility
26April2019 – Looking NE to SW across facility
26April2019 – Looking E to W along N office wall
26April2019 – Looking E to W along S wall of office wing
26April2019 – Looking N to S along E wall
26April2019 – Looking NE to SW across bathrooms and conference center
26April2019 – Conduit outside server room
26April2019 – SE corner of facility
26April2019 – Trash center and rear stairs at SE corner
26April2019 – Looking S to N along W wall of conference center
26April2019 – Looking W to E along N wall of office wing
26April2019 – Looking NW to SE across office wing
26April2019 – Looking S to N from interior hallway
26April2019 – Looking NW to SE at stormwater pond
26April2019 – Looking E to W at stormwater pond
26April2019 – Looking SE to NW at stormwater pond
26April2019 – Stormwater overflow buried in trees
26April2019 – Looking E to W at soil berm in West Field
26April2019 – Looking W to E at soil berm in Center Field
Here’s a panoramic view taken from the contractor’s trailer.
Panoramic view of building site from contractor’s trailer
April 24, 2019
Concrete footings for posts and bollards being poured. Materials for framing are starting to arrive. The stormwater pond is taking shape.
24April2019 – Pouring concrete in front pillar forms
24April2019 – Looking E to W along north wall of office wing
24April2019 – Looking E to W along S wall of office wing
24April2019 – Looking N from server room to main entrance
24April2019 – Rebar will be bent 90 degrees to anchor slab on grade (SOG)
24April2019 – Mud room entrance at S end of building
24April2019 – Conduit to extend electrical service to outbuildings
24April2019 – Conference at stormwater pond
24April2019 – Stormwater pond will be planted when finished
24April2019 – Framing lumber is arriving
24April2019 – Rebar for concrete work
24April2019 – Pilasters for S and W edge of outdoor plaza
24April2019 – Pilasters for S and W edge of outdoor plaza
24April2019 – Post footings for covered walkway – S side of office wing
24April2019 – Covered walking footings – Outside conference center
24April2019 – Walkway footings and interior post footings
24April2019 – W end of office wing (“west wing”)
24April2019 – W end shows post footing at the second front entrance
24April2019 – Soil berm along Beavercreek Road
April 19, 2019
Radon system and base covered with plastic under office wing. West end of office wing formed for concrete. Essentially all of the under-slab plumbing is done. We expect the slab to be poured around Thursday, May 2.
19April2019 – Looking E to W along front of office wing
19April2019 – Looking E to W from lobby through office wing
19April2019 – Looking E to W from bathroom along back of office wing
19April2019 – Looking NE to SW across break room toward rear stairs
19April2019 – Trash and recycle center near rear stairs
19April2019 – East side of rear stairs
19April2019 – West side of rear stairs
19April2019 – Bent rebar at south wall will reinforce the concrete slab
19April2019 – Looking NW to SE across the office wing
April 17, 2019
More work on utilities and under-slab systems. The requirement for an active radon collection system is new. We’ll have a fan in the attic that pulls any radon up from under the slab before it can enter the interior of the building.
17April2019 – OAC team examining construction details
17April2019 – Looking N to S at main entrance. White perf pipe is for radon control.
17April2019 – Looking E to W along front of office wing
17April2019 – Looking E to W from bathrooms toward south side of office wing
17April2019 – Looking W to E at covered walkway along rear of office wing
17April2019 – Looking from office wing toward USDA space on west end
17April2019 – Looking from USDA end into office wing
17April2019 – Unsecured box for in-floor power
17April2019 – Worker securing placement of floor box
17April2019 – Secured floor box
17April2019 – Trash center at SE corner of building.
17April2019 – Can you find the horizontal orange line? That shows the final elevation of the building slab.
17April2019 – Rear steps and trash center.
17April2019 – Rear steps and trash center.
17April2019 – Server room layout.
17April2019 – More conduit!
April 12, 2019
Most of our staff were out for the week at an annual statewide training event. These photos represent progress since the April 5 photo set. Forms continue to go up. Concrete was poured for the south wall today. Plumbing and conduit is being placed before the floor slab is poured.
12April2019 – Looking E to W along front of building
12April2019 – Looking E to W along waste line under office wing
12April2019 – Looking E to W along south side of office wing
12April2019 – Looking W to E along south side of office wing
12April2019 – Riser in NW corner of office wing
12April2019 – Contractor building forms
12April2019 – Location of stormwater retention pond
12April2019 – Foundation wall on S end of E wing
12April2019 – Server room work
12April2019 – Server room
April 5, 2019
These photos were taken on Saturday, April 6, and represent the end-of-day progress on April 5. The building outline is taking shape!
5April2019 – View of site from contractor trailer
5March2019 – Looking NE to SW from front entryway
5March2019 – Footing for front entryway post
5March2019 – Form detail for front entry post footing
5March2019 – Looking E to W across front of building
5April2019 – Looking E to W across back of office wing
5March2019 – Looking NW to SE across office wing
5April2019 – Form for interior post footing
5April2019 – Looking at future bathrooms and break room
5April2019 – More boulders
5March2019 – Trash and recycle center at back door
5April2019 – Trash center and back door steps
5April2019 – Another big boulder
5April2019 – Location of stormwater detention pond
5April2019 – Stormwater outfall before installation of collection box
5April2019 – Looking S to N from lobby up driveway toward Beavercreek Road
5April2019 – Stormwater drain
Panoramic view from the contractor’s trailer, looking north to south.
Panoramic view from the contractor’s trailer, looking north to south.
April 4, 2019
More work on footings and forms for the foundation today. We expect to see concrete being poured starting on Tuesday, April 9 (weather permitting). And the boulder family keeps growing!
4April2019 – Concrete forms outline the office wing
4April2019 – Looking E to W along S side of offices
4April2019 – Looking W to E along S side of offices
4April2019 – Subcontractor trailers are showing up on site
4April2019 – The boulder family is growing!
4April2019 – Landscaping windrow along Beavercreek Road is growing
April 3, 2019
Significant progress today on forming footings and foundation walls. We also removed five trees so that we can excavate the required stormwater overflow trench. And a big boulder joined the boulder family.
3April2019 – Post footings and exterior wall form
3April2019 – Excavating for recycle and trash center
3April2019 – The excavated recycle and trash center location
3April2019 – Examining site of stormwater outfall trench
3April2019 – Logs for future barn repairs
3April2019 – More boulders
3April2019 – A BIG boulder joined the boulder family
3April2019 – Team confers east of building footprint
This is a 180-degree panoramic view of the building site from the southeast corner of the break room. As with other pano views, the angles are distorted. The driveway is coming toward you from the right side, past the contractor’s trailer.
180-degree panoramic view of the building site from the SE corner of the break room
April 2, 2019
The footings are being excavated and formed.
2April2019 – Looking at main entrance location
2April2019 – Looking S along E side of building
2April2019 – Looking W along N side (front) of building
2April2019 – Looking E along N side of building
2April2019 – Water line along S side of site
2April2019 – Boulders!
This is a partial panorama from the northeast corner of the building. The string lines are at 90 degrees; the pano view distorts the angle.
Panorama of the east (left side of photo) and north (right side) of the building, from the northeast corner